What a Major Apartment Renovation Includes: Scope, Sequence and Limits

Scope by seven work packages — usually included, depends on the apartment, usually separate — plus boundaries with shared property, the order of work and hidden-work checkpoints.

Related service
Contents
  1. How a major renovation differs from a cosmetic one
  2. What a major renovation includes: scope by work package
  3. Boundaries: the apartment, shared property and other specialists
  4. Sequence of work: why the order matters
  5. Hidden work: what to check before it is covered
  6. Materials and changes during the work
  7. Frequently asked questions
  8. Sources
Apartment during renovation with opened walls, a doorway and an exposed ceiling
Illustrative image. Photo: Olek Buzunov / Unsplash

Short answer. A major apartment renovation usually covers strip-out, new wiring and plumbing inside the apartment, wall and ceiling preparation, levelling the floor base, waterproofing wet areas and all finishes down to doors, sockets and sanitary fittings. Shared parts of the building — risers, ventilation shafts, load-bearing structures and the facade — are not the apartment owner’s decision alone, so they are agreed separately. RigaBuild prepares the exact scope of work and the estimate after a site visit.

Key points

  • A major renovation is not just new surfaces: it includes services that end up hidden inside walls and floors.
  • Before the estimate, agree the boundaries: what belongs to the apartment, what is shared property of the building, and what another specialist does.
  • Check and photograph hidden work before the finishes cover it.
  • Some works need a procedure with the municipal building authority (būvvalde) — find out before work starts.

How a major renovation differs from a cosmetic one

A cosmetic renovation refreshes what you can see: paint, wallpaper, flooring, skirting. A major renovation also deals with what sits behind the finishes: wiring, water and drainage pipes inside the apartment, the floor base, partitions and bathroom waterproofing. That makes it one connected project rather than a list of separate jobs. If you lay a new floor first and only then decide to rewire, part of the new work has to be opened up again.

Not sure which type your apartment needs? Compare the signs in “Major or cosmetic renovation”.

What a major renovation includes: scope by work package

The table splits the work into three groups. Usually included — without it the renovation is not complete. Depends on the apartment — decided after the inspection or by your choices. Usually separate — work for another specialist, a decision of the building’s owners, or a separate contract.

PackageUsually includedDepends on the apartmentUsually separate
1. Strip-out and preparationremoving old finishes, floor coverings and fittings; carrying out debris; protecting common areasremoving partitions; taking the old floor base down to the slaba skip, if it cannot be placed by the building (agreed with the building manager)
2. Electricalnew wiring inside the apartment; boxes, sockets, switches; wiring layoutnew consumer unit; dedicated circuits for the hob, washing machine, underfloor heatinghigher supply capacity and connection to the riser or meter (distribution network operator, building manager)
3. Water and drainagepipework from the apartment’s shut-off valves to the fittings; drain connections inside the apartmentnew shut-off valves; new fitting positionsrisers and their replacement (shared property — agreed with the building manager)
4. Walls, ceilings, partitionsplaster repair or plasterboard lining; skimming; primingnew partitions; suspended ceilings; sound insulationwork on load-bearing walls — only after the building-authority procedure
5. Floorslevelling the base; new flooring; skirtingunderfloor heating; strengthening the floor structure in older buildings—
6. Bathroom and wet areaswaterproofing; tiling; installing sanitary fittingsreplacing the bath with a shower; concealed toilet framecleaning or repairing the ventilation shaft (shared property)
7. Finishingpainting; doors and architraves; socket and switch plates; cleaning before handoverkitchen installation; connecting built-in applianceswindow replacement where the facade is restricted; made-to-measure furniture
An indicative split. The actual scope is fixed in the estimate and contract appendices after the site visit.

This table is not a price list. What each package costs, and why the final estimate differs from a price per m², is explained in “Apartment renovation cost in Riga”. For the structure of an estimate with two illustrative scenarios, see the renovation estimate example.

Boundaries: the apartment, shared property and other specialists

In an apartment building, not everything inside your flat belongs to you alone. Risers, ventilation shafts, load-bearing walls and floor slabs, and the external walls are shared property of the building. A renovation contract alone cannot change them: you need the building manager’s agreement or a decision of the owners’ association, and in some cases a building-authority procedure as well.

  • Before the estimate, ask the building manager when the risers were last replaced and whether a building-wide replacement is planned. If it is, it usually makes sense to connect the apartment’s plumbing afterwards.
  • Ventilation: the bathroom and kitchen shaft must not be blocked or connected to a cooker hood without approval.
  • Power supply: if you need more capacity, this is handled with the distribution network operator, not only inside the apartment.

Which works need a notice or an explanatory memorandum at the building authority is summarised in “Documents before an apartment renovation”. In Soviet-era blocks, take extra care with load-bearing walls — see “Renovating a Soviet-era apartment in Riga”.

Sequence of work: why the order matters

  1. Inspection and measurements. Assess walls, floors, wiring and pipes, and any building restrictions.
  2. Decisions that shape the hidden work. Socket and light positions, kitchen and bathroom layout, appliance list. Make them before the strip-out, not after.
  3. Estimate, contract and appendices. Scope, who buys which materials, schedule and how changes are handled.
  4. Strip-out. It often reveals conditions that could not be seen before; these are documented and agreed in writing.
  5. First-fix services. Electrics, water, drainage; checked before they are covered.
  6. Walls, ceilings, floor base. Wet trades and drying time.
  7. Waterproofing and tiling in wet areas.
  8. Finishes. Painting, flooring, doors.
  9. Installing and connecting fittings and appliances.
  10. Handover. Checked against the agreed scope and signed off with an acceptance certificate.

As a rough guide, a major apartment renovation takes 4–9 weeks. The real duration depends on the floor area, condition, scope, approvals, deliveries and how quickly decisions are made. More in “How long does an apartment renovation take”.

Hidden work: what to check before it is covered

The most valuable part of a major renovation is invisible after handover. Check it while changes are still possible. Use this list to agree interim checks with your contractor in advance.

CheckpointWhenWhat to check and keep
Electricalbefore plastering or liningboxes and runs match the plan; wiring layout; photos of cable routes with a tape measure
Water and drainagebefore coveringpressure-test result; falls; access to shut-off valves; photos
Waterproofingbefore tilingcorners and pipe penetrations; upstands on the walls; photos
Floor basebefore laying the flooringflatness checked with a straightedge; moisture requirements for the chosen flooring
Partitions and liningsbefore skimmingfixings for heavy furniture and appliances; sound insulation, if agreed
Photos and measurements are useful years later, when you need to put up a shelf or find a pipe.

Materials and changes during the work

RigaBuild prices cover labour; materials are paid for separately. You can buy them yourself, or RigaBuild can buy them, in which case available wholesale terms may apply. The estimate should make clear who buys what and when, because deliveries affect the schedule. More in “Renovation materials: who buys them”.

Extra work is more common in a major renovation than in a cosmetic one, because some conditions only show up after the strip-out. Put every change in writing before it is carried out — see “Change orders and extra work”. Completed work is handed over with an acceptance certificate, and warranty terms are set by the contract.

Frequently asked questions

Does a major renovation always mean rewiring the whole apartment? Not always, but in older buildings with aluminium wiring or no earthing it is usually justified. The decision follows the inspection, not just the age of the building.

Can a major renovation be done in stages? Yes, if the order is planned so that the next stage does not require opening up the previous one. Services are usually best done across the whole apartment at once.

What counts as shared property? Typically risers, ventilation shafts, load-bearing structures and external walls. Check the specifics for your building with the building manager.

Is a site visit needed before the estimate? Yes. Without one, only an indicative starting price can be given; the final figure depends on the actual condition and the agreed scope.

Sources

Prices and timescales — RigaBuild Pricing page and the Major apartment renovation service page (accessed 06.11.2026).


Want to define the scope for your apartment? See our major apartment renovation service and request an estimate — we prepare the list of works after a site visit. The indicative starting price for a major renovation is from €300/m² (labour, excluding VAT).

Prepared by the RigaBuild editorial team. Prices, timescales and sources checked on 6 November 2026. This article is for information only and does not replace legal advice or an answer from the building authority.